The building process summarised

ABC builds all its floating properties in a fully conditioned environment. Within this industrial environment, our primary concerns are always innovation of the building process, sustainable construction, energy efficiency for residents and quality improvement. Weather conditions have no impact on the construction work and so the building process is efficient and effective.

Step-by-step plan

  1. Formwork
  2. Placing reinforcement
  3. Pouring concrete walls and floor
  4. Removing formwork, drying time
  5. Start of superstructure, interior and exterior walls
  6. Adding storeys
  7. Windproof and watertight
  8. Finishing, painting, sanitary facilities, etc.
  9. Preliminary delivery with the Eigen Huis association
  10. Transport to anchorage site
  11. Final delivery
  12. Follow-up